2017
Raising the Roof on LifeTown
Jun30
Work continues throughout LifeTown with the new roof structure being constructed. As the summer heats up the ducts for the air system are being hung and the 5 skylights in Life Village have been installed. The underpinning for the lower level is complete and the new drain pipes are being installed. The main entrance is also starting to take shape.Read More
2017
Day by day, week by week, LifeTown is coming to life…
Jun29
Time lapse video of the shower floor being poured.Read More
2017
2017
Site work begins at LifeTown
Jun12
Construction at LifeTown is heating up on many fronts. Site work has begun with the (former) upper parking lot becoming a great outdoor ballfield and the new driveway entrances being cleared. Read More
2017
Another week of great progress at LifeTown!
May19
Gym roof is up, lower level wall is almost finished and interior walls are starting to go up... another week of great progress at LifeTown!Read More
2017
Construction at LifeTown is moving along very nicely
May12
Steel frame for the gym is in place and the gym will be closed in next week. Entry level excavation is complete and the footings are being poured for the new wall. Skylights and air ducts are being installed.Read More
2017
ShopRite comes on board as partners
May01
We are proud to announce that Wakefern Food Corp./ShopRite has come on board as partners!
With construction well underway we look forward to the grand opening this fall.Read More
2017
Hollister Construction was very busy this week
Apr28
Hollister Construction Services contractors were very busy this week at LifeTown digging the entry level, building the steel frame for the gym and multipurpose room, and working on the roof skylights and air systems.Read More
2017
LifeTown construction is moving along nicely
Apr21
The gym wall is complete and ready for the new roof. The temporary support is in place and the entry level will be dug starting next week.Read More
2017
It was a busy week at the LifeTown construction site.
Apr07
New concrete supports have been poured and the drain pipes have been installed. The gym wall is nearly complete and the entry level is being prepped for excavation.Read More